Each process asset listed in the PAL is in one of the following five states of development. The table below explains these states in greater detail.
| Sequence # | Status Designation | Status Description |
|---|---|---|
|
0 |
582 rescinded | This asset has been "un-baselined" by the Code 582 CCB. |
|
1 |
Not started | No significant work has been done on this asset. |
|
2 |
In progress | Work has begun on this asset. Note: For Codes 580 and 588, this status replaces both the "outline" and "draft" status designations used previously. |
|
3 |
Final | A final draft of the asset has been completed. Final drafts still must be submitted for EPG and Branch review. For tools, the final prototype has been completed. NOTE: Some final drafts are posted in the PAL. These documents are version-controlled, but not yet CCB-approved. |
|
4 |
EPG approved | This asset is version-controlled by the EPG. |
|
5 |
CCB approved | The CCB (ISD, FSB, or other 580 CCB) has formally approved this asset. |
|
6 |
588 approved | The asset has been approved for publication by Code 588 and is under 588 version control. |
|
7 |
300 approved | This asset has been approved for publication by Code 300 and is under Code 300 version control. |
|
8 |
GSFC approved | This asset is available via GDMS. |